NHPC#39;s 50 MW solar project in Tamil Nadu synchronised with grid

From The Web - India
Typography

State-run NHPC today said it has synchronised a 50 MW solar PV project at Theni/Dindigul...

Advertisement

State-run NHPC today said it has synchronised a 50 MW solar PV project at Theni/Dindigul district of Tamil Nadu with the grid.

The project was synchronised with the grid last month in presence of the commissioning team consisting of senior officers from TANGEDCO and the NHPC project officials, an NHPC statement said.

The Power Station has generated 6.87 MU (million units) up to April 15, 2018. The solar project shall provide an annual generation of 105 MU with sale of entire power to the TANGEDCO in accordance with the power purchase agreement.

The project was executed on EPC (engineering procurement and construction) basis with a time frame of nine months. Domestically manufactured Solar PV modules are used for the project, it added.

Continue Reading On Money Control


Translator

SolarQuarter Tweets

Follow Us For Latest Tweets

SolarQuarter SolarQuartersBestCompaniesToWorkFor Congratulations to all the winners! AMPL Cleantech Avaada CleanMax Solar Froni… https://t.co/GJ1Mwz4i5G
Monday, 16 July 2018 11:09
SolarQuarter SolarRoofs Event Now In Jaipur_100+ Installers & Consumers Attending SolarRoofs Rajasthan_Register Now, 20 July 201… https://t.co/qKnqOMDhz6
Saturday, 14 July 2018 03:31
SolarQuarter SolarRoofs Event Now In Jaipur_100+ Installers & Consumers Attending SolarRoofs Rajasthan_Register Now, 20 July 201… https://t.co/CzxDYBBIvP
Friday, 13 July 2018 06:05